Upper Coonamesset River Wetlands Complex

  • Property
posted on August 27, 2025

We installed EC-5 sensors at this plot ~2 pm on 8/26/2025.

Asset tags and corresponding depth for the LO sensors:

    • asset: 8
    • depth: 5 cm
    • asset: 9
    • depth: 15 cm
posted on August 27, 2025 (updated August 27, 2025)

We installed EC-5 sensors at this plot ~2 pm on 8/26/2025.

Asset tags and corresponding depth for the LO sensors:

    • asset: 6
    • depth: 5 cm
    • asset: 7
    • depth: 15 cm
posted on August 27, 2025

We installed EC-5 sensors at this plot ~2 pm on 8/26/2025.

Asset tags and corresponding depth for the LO sensors:

    • asset: 4
    • depth: 5 cm
    • asset: 5
    • depth: 15 cm
posted on August 27, 2025 (updated August 27, 2025)

We installed EC-5 sensors at this plot ~2 pm on 8/26/2025.

Asset tags and corresponding depth for the LO sensors:

    • asset: 10
    • depth: 5 cm
    • asset: 11
    • depth: 15 cm
posted on August 26, 2025

Installed soil probes 00004 (5cm) and 00005 (15cm). Gravely/sandy with est. 20% organic (CH)

posted on November 12, 2024

Design and permitting is complete. The project is out to bid for construction.